Task procedure
- Customer inquiry (Sales, business)
- Consultation with the consumer (Selecting item, setting the producing volume by item, selecting equipment, installation location and drawing for estimate acceptance)
- Preparation of proposal (drawing for estimate, estimate sheet, company introduction, instructions)
- Proposal Submit (Consumer inspection and consultation, production and submit of final proposal after supplementation and decision of consultation)
- Contract
- Preparation of on-site survey, working drawing and specifications
- Preparation of machine and electricity Part List, Outsourcing Part List
- Outsourcing Part List Order and Parts Order, Outsourcing Process Order
- Warehousing
- Manufacture (Welding, assembling, mapping, trial run)
- Transport, installation, trial run and driving education
- Trial run completion report and delivery confirmation seal
- Payment completion and tax invoice issue
- A/S post management
※ If it is facility line, it takes 50~70 days in average (item 6~13)